Nvidia B300 Lead Times Hit 26-40 Weeks: AI Accelerators Squeeze RTX 50 Supply, RTX 60 Timeline May Slip
TL;DR
On November 25, 2026, China's Commercial Times reported that lead times for new Nvidia B300 orders have stretched to 26-40 weeks, with GB300 at about 14-26 weeks. The same supply-chain reporting says consumer GeForce RTX 50 shipments are being gradually cut, and the RTX 60 series — originally targeted for mass production at the end of 2027 — may slip further.
The one-line reason: ODM capacity is being redirected toward AI accelerators and the Vera Rubin platform, which is entering volume delivery, while server DRAM is also taking the advanced fabs away from GDDR7 memory. This piece lays out the key numbers, who is affected, which misreadings to avoid, and the three moves to make. This article is compiled from multiple media reports.
How to use this report: what actually happened
Per ODM sourcing quoted in the Commercial Times, Nvidia's main manufacturing partners are shifting capacity toward three lines: B300, GB300, and the Vera Rubin platform as it moves into volume delivery. Some AI server and workstation products are still shipping on schedule, but wait times for new orders have climbed noticeably.
| Product line | Lead-time change |
|---|---|
| B300 new orders | 26 to 40 weeks |
| GB300 new orders | 14 to 26 weeks |
| DGX Station with desktop GB300 | about 26 weeks |
| RTX Pro server / workstation accelerator cards | more than 26 weeks |
| GeForce RTX 50 gaming GPUs | shipments being gradually cut |
| GeForce RTX 60 | originally targeted for end-of-2027 mass production; timeline may slip further |
Supply-chain estimates put delivery of most projects ordered in the last two quarters at Q2-Q3 of 2027.
Memory is also under pressure. Storage makers are allocating advanced capacity to server DRAM first, which constrains GDDR7 output for graphics cards and has pushed prices higher. IT Home added a detail worth noting: after PC prices rose, sales softened in Asia and Europe, North American channel inventories grew, and some brands are already re-evaluating memory purchases for Q1 2027.
Nvidia has previously said GeForce demand remains strong and all models continue to ship, but memory supply tightness remains a key factor affecting product availability.
Who this is for
This piece is useful for:
- Individual builders and upgraders watching RTX 50 stock over the next few months
- Board channel partners and OEM brands recalibrating 2027 inventory and procurement plans
- Enterprise buyers of AI workstations or DGX Station who need to lock delivery dates into contracts
Not a good fit for
- Owners of current-gen cards who have no plans to upgrade this year
- Hyperscale data centers buying on long-term contracts — a 26-40 week lead time was already baked into their planning
Pitfalls: three misreadings to avoid
Misreading 1: AI-card shortage means gaming cards will get more expensive. This is a capacity reallocation, not an official price hike. AI accelerators and consumer GPUs share ODM lines; B300/GB300/Vera Rubin are absorbing that capacity, so RTX 50 shipments shrink rather than Nvidia raising prices. Whether retail prices move depends on channel inventory and how fast GDDR7 price increases pass through, and there is no official price-increase statement in the public reporting.
Misreading 2: "Longer lead times" means "no longer sold." The reporting says RTX 50 supply is being gradually cut and the RTX 60 timeline may slip further, not that products are discontinued. Board makers will likely keep existing products on sale to sustain the business.
Misreading 3: GDDR7 pressure is a one-off blip. The server-DRAM-first allocation is a structural capacity decision, not a temporary hiccup. As long as AI server DRAM demand keeps climbing, GDDR7 stays lower in the priority stack.
Cost and time: how long to wait, how much it costs
- Lead times: B300 new orders 26-40 weeks (roughly 6-10 months); GB300 14-26 weeks; most projects ordered in the last two quarters deliver in Q2-Q3 2027
- RTX 60 mass production: originally targeted for end of 2027, may slip further; no new public timeline
- GDDR7 memory: prices continuing to rise; no official figures on the magnitude or duration
- Zero-cost takeaway: this report does not change the value of hardware you already own; it changes your expectations for a 12-18 month upgrade cycle
Next step
First move: if you are building or upgrading within the next 3-6 months, track channel stock prices and GDDR7 price trends now. Don't wait for an official price-increase notice. RTX 50 supply cuts mean the floating channel inventory gets thinner and price elasticity gets bigger.
Then:
- Enterprise buyers of AI workstations or accelerators: write 26-40 week lead times into contract delivery terms instead of vague "as soon as possible" language
- Board channel partners: re-evaluate Q1 2027 memory and GDDR7 purchase volumes; reporting notes some brands are already doing this
- Fold the Vera Rubin platform into your 2027 evaluation; it is entering volume delivery and will be the key variable in the next capacity-allocation cycle
Sources
- Phoenix Tech / IT Home: https://tech.ifeng.com/c/8yL5KTIrOoh (2026-11-25 13:22:17 +08:00)
- 17173 Gaming News / IT Home: https://news.17173.com/content/11252026/133035331.shtml (2026-11-25 13:30:35 +08:00)
- BigGo Finance: https://finance.biggo.com/news/b08b60b1-f5a3-4106-9f08-c1a9d30c8431 (2026-11-25 02:26:27 UTC)
- Original source: China Commercial Times, 2026-11-25 (compiled from multiple media reports)